Subway progress in the Panama City using the boring machine MARTA:

Panama America News, subway progress in Panama City using the boring machine MARTA:

'Martha' will arrive in January at the Church of Carmen station

17 | 11 | 2012

'Martha' will arrive in January to the Church of Carmen Wait. Some stayed to watch out for "Marta." (Carlos Lemos)
Edith Erika Quiñones (erika.quinones @ epasa.com) / PANAMA AMERICA

Logistics disarmament

  • In the season of Carmen Church holes have been left on the track to get the components of the TBMs, once they reach this point. In late March should have removed the two machines.

Panama America News, subway progress in the Panama City using the boring machine MARTA:

'Martha' will arrive in January to the Church of Carmen

17 | 11 | 2012
'Martha' will arrive in January to the Church of Carmen Wait. Some stayed to watch out for "Marta." (Carlos Lemos)
Edith Erika Quiñones (erika.quinones @ epasa.com) / PANAMA AMERICA

Logistics disarmament

  • In the season of Carmen Church holes have been left on the track to get the components of the TBMs, once they reach this point. In late March should have removed the two machines.
After traveling 2000 700 meters and 10 months of operations, the TBM Marta (boring machine-LS)) arrived yesterday at the St. Thomas hospital station on Avenida Justo Arosemena.
MARTA's arrival was scheduled for 10:30 am, but it was not until 24:30 (12:30 midnight) that the boring machine arrived at the station, where MARTA was greeted by a large audience, among whom were the National Police director, Julio Moltó; Irvin Halman, President of the Chamber of Commerce, Industries and Agriculture of Panama, and Roberto Troncoso, president of the Panamanian Association of Business Executives.
Agustin Arias, head of Engineering at Metro Department, explained that this time was a "slow-motion collapse" because, as the wall was reinforced with fiberglass, the TBM had to put a ring more to break it.
He said that "Carolina" (MARTA?-LS) escalates about 300 meters excavated 2000 and in the third week of December should reach the station Carmen Cathedral oin Via Espana, where "Marta" should be in late January and complete building the underground section.: